M/S LION ENGINEERING CONSULTANTS PVT. LTD. ... Petitioner(s)
VERSUS
THE STATE OF MADHYA PRADESH and others ... Respondent(s)

OFFICE REPORT OF FRESH CASE
1. The details of the case before the Trial Court are as follows:
S.No. Court State Bench Case No. Order Date
           

2. The details of the case before the High Court as well as the limitation report are as follows:
S.No. Court State Bench Case No. Order Date Petition in Time Delay Days Filing Delay Days Re-filing
1 High Court MADHYA PRADESH High Court of Madhya Pradesh Principal Seat at Jabalpur ARBA-23-2020 03-10-2024 Yes
12 days

3. The Advocate on-record for the petitioner/appellant has also filed following document(s)/ Interlocutory application(s):
S.No. Application No. Description of Document Filing date Verification Status Page No.
1 23767-2025 EXEMPTION FROM FILING O.T. 27-01-2025

2 23768-2025 CONDONATION OF DELAY IN REFILING / CURING THE DEFECTS 27-01-2025

3
26004/2025PERMISSION TO FILE ADDITIONAL DOCUMENTS/FACTS/ANNEXURES29-01-2025


4. The similarity found in the present case is based on:
S.No. Diary No. Case No. Cause Title Status Remarks
1
10534/2015C.A. No. 008984 - 008985 / 2017 
SLP(C) No. 015703 - 015704 / 2015 
S.L.P.(C)...CC No. 008089 / 2015
M/S LION ENGINEERING CONSULTANTS vs. THE STATE OF MADHYA PRADESH AND ORS
Disposed of on 22.03.2018
(Annexure P-9, Page no. 108-113)
Referred at Annexure P-9 , filed against Annexure P-6 and Annexure P-7
2
39542/2010 C.A. No. 000974 / 2012 
S.L.P.(C)...CC No. 019782 / 2010 
SLP(C) No. 000907 / 2011
MP RURAL ROAD DEV. AUTHORITY . AND ANR vs. M/S. L.G. CHAUDHARY ENGINEERS AND CONT.
Disposed of on 08.03.2018
(Annexure P-8, Page no. 98-107)
Referred at Annexure P-8
3
2113/2019 C.A. No. 000204 / 2020 
SLP(C) No. 004789 / 2019
M/S JMC PROJECTS (INDIA) LTD. vs. MADHYA PRADESH ROAD DEVELOPMENT CORPORATION
Disposed of on 10.01.2020
(Annexure P-11, Page no. 142-143)
Referred at Annexure P-11
4
23860/2019C.A. No. 003736 / 2020 
SLP(C) No. 017642 / 2019 
M/S SWETA CONSTRUCTION vs. CHHATTISGARH STATE POWER GENERATION COMPANY LIMITED
Allowed on 25.08.2022(Annexure P-13, Page no. 159-169)
Referred at Annexure P-13
5. In terms of Order XV Rule 2 of the Supreme Court Rules, 2013, the status of proof of service upon the respondent(s)/caveator(s) is as follows:-
S.No. Respondent(s)/Caveator(s) Status of proof of service Date of Service
No Information Available
6. It is submitted that counsel for the petitioner has on 29-01-2025 filed an application seeking permission to file additional documents alongwith the documents. The same is being circulated for kind perusal of the Hon'™ble Court.

7. The special leave petition along with the above-mentioned application(s) is listed before the Hon'ble Court with this Office Report.

DATE:29-01-2025

ASSISTANT REGISTRAR

Copy to :-

1